How to Get a MEPCO New Connection – Step by Step Guide

Are you planning to get a MEPCO new connection for your home, shop, or business? You’re in the right place! This guide explains everything in simple words, so you can avoid stress and save time.

Whether you need a small connection for your home or a large connection for your business, the process can be confusing. But don’t worry—I’ll walk you through every step.

Ways to Apply for a MEPCO New Connection

You can apply for your new connection in two ways:

By visiting the MEPCO office, go to your nearest office and collect the application form.

Online through the official website – This is easy and saves you time. Here’s the link to apply online directly:
Apply for New Connection – MEPCO e-Application

Screenshot of the online MEPCO new connection application form.
Sample MEPCO online connection form for quick application

Documents You Need

Before starting your application, keep these documents ready:

  • Proof of property ownership (e.g., registry, utility bill)
  • Undertaking form (signed by applicant)
  • Power of attorney (if there’s more than one owner)
  • No Objection Certificate (if you’re a tenant)
  • Copy of your CNIC (Computerized National Identity Card)
  • Copies of CNICs of two witnesses (only needed for three-phase connections)
  • Signed copy of the relevant tariff

Steps to Apply for New MEPCO Connection (Online)

Here’s how you can apply online:

Step

Action

1

Visit the online portal and choose your connection type.

2

Select “MEPCO” in the Distribution Company list.

3

Fill out the form with all required details.

4

Upload scanned copies of the documents listed above.

5

Submit the form and print a copy for your records.

6

Submit the printed form and documents to your nearest MEPCO office.

7

Wait for MEPCO to check your papers and issue a demand notice.

8

Pay the demand notice fee at the designated bank.

9

Submit proof of payment back to the MEPCO office.

10

MEPCO will install your new connection after verifying your payment.

Estimated Time for New Connection

The time it takes depends on how much load (electric power) you need:

Category 1 – Up to 15 kW (Small Homes/Businesses)

  • Total estimated time: About 30 days

Category 2 – 16 to 70 kW (Medium Businesses/Offices)

  • Total estimated time: Around 44 days

Category 3 – 71 to 500 kW (Large Factories/Industries)

Total estimated time: Up to 73 days

Cost of a MEPCO New Connection

Costs vary depending on your connection size, distance from the main supply, and other factors. Generally, you’ll pay:

  • Connection charges
  • Security deposit
  • Cost of wiring and installation material
  • Service charges

The exact amount will be listed in your demand notice from MEPCO. Always keep some extra budget for unexpected costs.

Real-Life Example

Let me share a simple example:
Ali from Multan applied online for a new single-phase MEPCO connection for his small shop. He uploaded his property documents and paid his demand notice of around Rs. 10,000. His connection was installed in about 28 days. He said doing it online saved him many trips to the office!

Common Mistakes to Avoid

Missing documents – Double-check that all your papers are complete.

Not following up – Visit or call the office to check your application status.

Delaying payment – Pay your demand notice quickly to avoid delays.✅ Incorrect details – Enter your name, address, and CNIC exactly as shown on your official documents.

Frequently Asked Questions (FAQs)

Visit your nearest office or call the MEPCO helpline. Some regions also allow online tracking.

You must submit physical documents to the office even if you start your application online.

For small home connections, around 30 days. Bigger connections take longer.

At present, MEPCO does not offer a fast-track service for new connections.

Final Thoughts

Applying for a new MEPCO connection might feel complicated, but with the right steps, you’ll have your electricity running in no time.

Need more help? Drop your questions in the comments or contact your nearest MEPCO office for official guidance.